Margalla Avenue Extension 43% Complete, CDA Says

Construction work under way on a road interchange in Islamabad (file photo).

Written by

in

Work on the Margalla Avenue extension and the Sangjani Interchange is 43 per cent complete, according to the Capital Development Authority. The authority shared the update in a statement on Monday, setting out the progress made so far on the two connected parts of the project.

The extension runs from N-5 to M-1, and it is about 2.7 kilometres long. According to the Capital Development Authority, the work lies within the limits of Islamabad Capital Territory, and the extension forms part of the road work now under way in the area.

The loops and ramps on the extension are nearing completion, the authority said. This part of the work has moved close to its finished stage, while other parts of the project continue at different stages of construction.

Structural work on the underpass has been completed, according to the Capital Development Authority. The concrete walls and footing slabs for the underpass have been finished, and earth filling is to start shortly, the authority said.

Work under way at Sangjani Interchange

At the Sangjani Interchange, piling has been completed and steel fixing is under way, according to the Capital Development Authority. The statement also said that piling and girder work have been completed at the interchange, and that excavation is nearing completion.

The progress at Sangjani Interchange therefore covers work below ground level as well as work on the structure above it. With piling completed, steel fixing is now under way, and excavation is close to completion, the authority said.

Work is also progressing on the abutments of the N-5 bridge. According to the Capital Development Authority, piling and excavation for the abutments are progressing, and this work forms part of the wider construction taking place alongside the extension and the interchange.

Taken together, the update places overall progress on the Margalla Avenue extension and the Sangjani Interchange at 43 per cent. The Capital Development Authority said the extension is about 2.7 kilometres long, the loops and ramps are nearing completion, the underpass structure is complete, and work at the Sangjani Interchange and on the N-5 bridge abutments is continuing.

According to APP, the statement was issued by the Capital Development Authority on Monday. The authority did not set out a completion date in the update shared in the statement, and the figures given relate to the progress reported at this stage of the work.

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *