Tarbela Tunnel: International Consultants to Probe Incident

Water and dust gushing inside the Tarbela 5th Extension tunnel excavation site after the rock collapse.

Written by

in

The federal government has decided to hire international consultants to find out the causes of the tunnel incident at the Tarbela 5th Extension hydropower project, 24NewsHD and PakVoices reported on 18 November 2026.

According to government sources, the federal government has contacted international consultants to investigate the incident and has informed them about the current status of the project. The sources said the consultants are likely to be hired soon, adding that it will take time to establish the root causes of the incident.

The incident took place on 9 November, when a weak section of rock collapsed during the excavation of the second bench of the project’s connecting tunnel. Water from the intake pit entered the tunnel and the under-construction powerhouse, according to the Water and Power Development Authority (WAPDA).

All workers, Pakistani and Chinese, were evacuated safely. WAPDA said there was no damage to the main tunnel, the powerhouse, the tailrace culvert or the switchyard, and no threat to the main dam. Reports on social media claiming that the dam had collapsed were false, and work at the site has been suspended while an inquiry is under way.

Second failure at the same project

The incident is the second serious failure at the Tarbela 5th Extension, known as T-5. An earlier inquiry into a cofferdam collapse in July 2026 held the Chinese contractor, the consultant and WAPDA jointly responsible. The project converts Tunnel 5, originally built as a low-level irrigation outlet, into a power tunnel with a new powerhouse of three 510-megawatt units, giving a total capacity of 1,530 megawatts.

The cost of the project has climbed from about Rs82 billion to more than Rs316 billion, and completion has slipped to 2028 or later, according to reports. The project has received international financing, including a World Bank loan of $390 million and $300 million from the Asian Infrastructure Investment Bank, while the civil works contract was awarded to China’s PowerChina.

The Ministry of Planning approved the revised cost of Rs316.41 billion on 2 November, only a week before the tunnel incident. Officials said the government wants the international experts to examine the technical causes of the incident and recommend measures to prevent such incidents in future.