Karachi Commissioner Syed Hassan Naqvi has suspended eight officials of the Sindh Building Control Authority (SBCA) after a six-storey under-construction building collapsed in the Admin Society area near Baloch Colony, AAJ News reported. Three people were killed and at least 10 others injured, according to officials.
The suspended officials include the director of Chanesar Town, all relevant deputy directors, an assistant director and a building inspector, according to the report. The suspensions were ordered as rescue teams continued their operation at the site of the collapsed building.
Commissioner Naqvi said the incident would be thoroughly investigated and that no one responsible would be spared. He said the rescue operation would continue through the night until the work at the site was complete.
Earlier, Sindh Chief Minister Murad Ali Shah visited the collapse site and reviewed the rescue operation. He said the building had been permitted only for ground-plus-one construction, but six floors had been built. “Where was the Sindh Building Control Authority?” he asked, questioning how such construction had gone ahead.
The chief minister said such extensive illegal construction could not happen without the involvement of government officials. He said the loss of life caused by illegal construction and negligence amounted to murder, and that officials found responsible, whether from the SBCA or the district administration, would face strict punishment and jail. He added that there would be no question of reinstating officials who had been suspended.
Shah also questioned the East deputy commissioner about other buildings under construction in the area. The deputy commissioner said builders had obtained court stay orders, a reply that angered the chief minister further, according to the report.
The collapse has once again raised questions about building regulation in Karachi, where unauthorised extra floors on under-construction buildings have repeatedly led to deadly accidents. The commissioner said the inquiry into the collapse would fix responsibility and that action would follow against anyone found negligent.
Rescue workers remained at the site through the night, searching the rubble for anyone still trapped under the debris, as officials said the operation would not be called off until the site had been fully cleared.